 |
|
NEWS
LINKS
All quiet at the moment.
We'll keep you posted
 |
|
|
TOWN
TOUR
|
|
|
|
|
The
foundations of the Esplanade were first laid in
the early 1880s using the rocks cut out of the
cliff during the construction of Cliff Hill.
It was originally 36 feet wide and gave access
to the beach via ramps at either end and flights
of wooden steps along its length. It proved
extremely popular and visitor numbers increased
dramatically so that by 1910 it was becoming
dangerously congested, especially at holiday
times, and plans were drawn up to widen it by
extending over the foreshore.
However, the oubreak of war meant that these
plans were not implemented until the mid 1920s,
when the Esplanade was widened to 60 feet and a
new curved sea wall constructed. New railings
were also erected and new seats installed and
the Esplanade was finally formally re-opened
with much pomp and ceremony on Empire Day, May
24th 1928.
Development of the buildings on the Esplanade
proceeded throughout the ensuing years, not all
of them meeting with universal approval,
particularly the large blocks of flats that
completely changed the seafront skyline.
But in 1987, the Esplanade pavement began to
crack and it was discovered that the concrete in
the sea wall was disintegrating. After much
hand-wringing by the Vale council (and,
typically, not much else), the position was
rescued by the Cardiff Bay Development
Corporation who funded the complete restoration
and refurbishment of the Esplanade.
A period of relative neglect followed with the
Esplanade suffering badly from the Vale
Council's strategy of what can only be described
as masterly inactivity. The one-way traffic
system was never properly finished, the railings
and the original tall, graceful lamp standards
were allowed to corrode badly, a lack of
engagement with the owners and erstwhile
developers of the Beachcliff building resulted
in its continuing deterioration, and the paving
on the restaurant side of the road became very
poor.
One major improvement was the restoration of the
exterior of the Pier Pavilion building, a major
project completed in the final months of 2006.
This work made an enormous difference to the
appearance of the building and transformed it
from a sad, dilapidated monument to poor
management back into something Penarth could
once again be proud of.
However, by 2009, the paint on the exterior had
started peeling badly and the buliding was again
looking dilapidated.
An exciting new initiative, launched by Penarth
Arts & Crafts Ltd (PACL) to restore the
interior of this beautiful landmark and create
an innovative, flexible and environmentally
sound attraction for South Wales unfortunately
failed in its first attempt to obtain lottery
funding, but a revised scheme was submitted and
in 2009 a grant of £99,600 was obtained for the
detailed preparation of a larger multi-million
pound grant application, which itself was
eventually successful.
Further details on the Pavilion project can be
found on the Penarth
Pier webpage.
Other elements of the Esplanade were also
greatly improved. Following correspondence
between the Society and Mr Miles Punter, the
Vale Head of Visible Services, the beautiful
ornate lamp pillars on the Esplanade were
expertly restored. These lamp pillars date from
the 1920s and were manufactured by Mackenzie &
Moncur Ltd of Edinburgh and Walter Macfarlane &
Co of Glasgow. New waste bins matching the
colour scheme of the lamp pillars and of a
sturdier and altogether more sympathetic design
were installed at more frequent intervals along
the Esplanade. The promenade railings were
repainted, and almost the whole of the pavement
on the restaurant side of the road was re-laid
with new paving slabs.
Also in 2009, the Seacot Hotel was taken over by
the proprietors of the very successful
Mediterraneo restaurant and renamed initially as the Waters
Edge, and later as the Pier and the Pebble, and
the Italian Shelter was acquired for
the development of a new restaurant, called the Fig
Tree.
The iconic Beachcliff building, however, which
had been covered in hideous protective green
netting for over 6 years, remained in a sad and
dilapidated condition, but a new project to
restore the building, providing luxury flats,
and a gymnasium to replace Chandlers pub,
received planning approval. It was hoped that
work would commence in late 2009, but by January
2010, very little had been done, prompting the
Vale Council to threaten legal action if the
development did not start quickly. After several
stops and starts, work is now
thankfully well under way.
The Esplanade is Penarth's jewel in the crown
and we look forward to the revitalisation of
Beachcliff and the Pier Pavilion to complete the
restoration of this unique seafront amenity.
|
|
|
|