|
|
|
|
|
The
block of shops and flats currently known as
Beachcliff was built by Victorian entrepeneur,
Frederick Speed, in 1904.
Originally, the block had private hotels at each
end, with the Gwalia Cafe situated at the
southern end and Govier's restaurant at the
northern end.
For many years, the building was owned by
the Rabaiotti family and was home to a
series of restaurants, some of which operated very successfully. But Beachcliff
eventually became a very troubled building.
In July 2003, concerns about the structural
integrity of parts of the frontage of the
building led to green netting being draped
across the upper storeys. And there it stayed,
the condition of the building having
deteriorated beyond the ability of the owners to
rectify it.
Then in January 2005, Decourcy Ltd, a Bristol
based development company submitted a planning
application to demolish the building and replace
it with a new cafe quarter complex at ground
floor level with apartments above. Following
intense lobbying against the proposals by local
activists over a period of several months
together with mounting planning difficulties,
the developer finally quit the project and we
ended up right back where we started.
Then, in August 2007, the local press reported
that the building had been purchased
from the Rabaiotti family by Cardiff based
developer RH Properties. Scaffolding was
then erected around most of the building as the developer
began essential repair work. A formal
planning application was submitted which would provide luxury flats in
the upper floors, with the Chandlers pub and
restaurant on the ground floor being replaced by
a gymnasium facility. However, the proposal was
intended to retain the character of the exterior
of the building.
By February 2010, most of the ground floor
establishments had been closed in preparation
for the start of development, and by May 2010
the preparatory demolition work was well under
way. However, concerns quickly grew that much
more of the building seemed to be being
demolished than had originally been anticipated.
The developer confirmed that serious structural
defects had been found and that their experts
had advised that the building could be
potentially dangerous.
Development then stopped
during negotiations between the developer and
the Council planning department until in August
2010 it was announced that a revised planning
application was being submitted. The objective
of maintaining the original appearance of Beachcliff's facade
was to remain central to the plan
and, where possible, original materials
recovered during the demolition phase were to be
reused. However, by the beginning of October, no
further development had taken place and the now
totally derelict building was in a worse state
than ever
Finally, in February 2011, demolition work
resumed. However, it was not long before work
again halted when it emerged that stonework on
the retaining wall that forms the rear boundary
of the site was loose. There was also
overhanging vegetation and both these matters
had to be resolved before work could proceed. It
was several months before the legal and
contractual procedures were settled and work
eventually started on the retaining wall at the
end of September 2011. This work was estimated
to take 12 weeks following which the main
construction work could recommence
We will continue to follow progress with great
interest.
|
|
|
|